Project Home > Project Expenses
Project Expenses
This information is based on project estimate: Page 1 & Page 2. The estimates are provided for all the three phases of the project.
Item |
Sq Feet |
Rate/Sq Feet USD |
Cost in USD |
|---|---|---|---|
Phase 1 |
|||
Toilet Blocks |
400 |
USD $18 |
$7200 |
Sanitation for Toilet Blocks |
400 |
USD $6 |
$2400 |
Dry Otta |
400 |
USD $3.5 |
$1440 |
Septic Tank & Inspection Chembers |
$1600 |
||
Total |
$12,640 |
||
Phase 2 |
|||
2 Classrooms |
2500 |
USD $18 |
$45,000 |
Total |
$45,000 |
||
Phase 3 |
|||
2 Classrooms |
TBD |
TBD |
TBD |
$57,640 |
|||